Daily report · 19 October 2026 · dictated on site by Omar- Started on Level 11 (ISO 27). 10A ISO 28 was still occupied, so the team moved to Level 8 (8B ISO 28) and then 10B ISO 28. 10A was fumigated as soon as it was released, left for about 15 minutes, then cleaned.
- Level 11 ISO 27: water was found dripping onto the floor. Possible sources are a square tank on the roof and the FCU side when the ceiling cover was opened. The source was not confirmed; the FCU (air-conditioning) side still needs to be checked.
- 8B ISO 28: usual work completed. FCU in good condition, no leaks, generally clean.
- 10B ISO 28: usual work completed. The exhaust filter housing sits outside the room, unlike the other rooms, so the team climbed the wall to reach it. Clear robot video recorded.
- 10A ISO 28: the exhaust-side filter opening was slightly damaged but could be opened. Both HEPA filters were removed, photographed and bagged. Filter removal is outside the scope; it was done for the first and the last room on the timetable.
Fumigated 11:34, dirty flexible duct labelled "Before" at 11:42; plenum and diffuser cleaned 14:33 – 14:39 and finished with the BMDT spray at the refitted louvre. Daily report, 19 Oct: water was found dripping onto the floor (possible sources: a square tank on the roof, or the FCU side when the ceiling cover was opened); the source was not confirmed. The report left this room's completion open, but the photo record shows the plenum, diffuser and louvre finished at 14:33 – 14:39.
Sanitisation ✓Before ✓In progress ✓After ✓
Before
Before19/10 11:42 · OmarLabel on photo: Level 11 iso 27 Before
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before After
After19/10 14:33 · OmarFinal BMDT spray at the refitted exhaust louvre (frame at 1s of site video) Sanitisation and cleaning in progress
Sanitisation19/10 11:34 · Omar
Sanitisation19/10 11:34 · Omar · 92s
In progress19/10 14:33 · Omar · 8s
In progress19/10 14:35 · Omar · 11s Robot inspectionDuct robot camera – exhaust riser9 min of riser footage (idle time removed from 24 min recorded)
All remaining photos and video clips for this room (5)
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before
In progress19/10 14:37 · Omar
In progress19/10 14:37 · Omar
In progress19/10 14:39 · Omar · 39s
Fumigated 11:52 (labelled room photo); dirty diffuser labelled "Before" 16:03; flexible duct cleaned and treated with BMDT 16:09 – 16:45. Daily report, 19 Oct: the exhaust filter housing sits outside the room, unlike the other rooms, so the team climbed the wall to reach it. Clear robot video recorded.
Sanitisation ✓Before ✓In progress ✓After ✓
Before
Before19/10 16:03 · OmarLabel on photo: 10 B Before
Before19/10 16:03 · OmarLabel on photo: 10 B Before After
After19/10 16:45 · OmarBMDT treatment applied to the flexible duct after cleaning (frame at 14s of site video)
After19/10 16:45 · OmarBMDT treatment applied to the flexible duct after cleaning (frame at 20s of site video) Sanitisation and cleaning in progress
Sanitisation19/10 11:51 · OmarLabel on photo: 10B Iso 28
Sanitisation19/10 11:52 · Omar · 54sLabel on photo: 10B Iso 28
In progress19/10 16:09 · Omar · 19s
In progress19/10 16:45 · Omar · 21s Robot inspectionDuct robot camera – exhaust riser14 min of riser footage (idle time removed from 20 min recorded)
All remaining photos and video clips for this room (2)
Sanitisation19/10 11:50 · OmarLabel on photo: 10B Iso 28
Before19/10 16:03 · OmarLabel on photo: 10 B Before
Full sequence with labelled before (15:07) and after (15:56) room and diffuser photos; exhaust plenum cleaned 15:10 – 15:18. Daily report, 19 Oct: FCU in good condition, no leaking, generally clean.
Sanitisation ✓Before ✓In progress ✓After ✓
Before
Before19/10 15:08 · OmarLabel on photo: level 8 before
Before19/10 15:07 · OmarLabel on photo: level 8 before
In progress19/10 15:10 · Omar
In progress19/10 15:10 · Omar After
After19/10 15:56 · OmarLabel on photo: level 8 after
After19/10 15:56 · OmarLabel on photo: level 8 after Sanitisation and cleaning in progress
Sanitisation19/10 12:01 · OmarLabel on photo: Level 8 ISO 28
Sanitisation19/10 12:02 · Omar · 65sLabel on photo: Level 8 ISO 28
In progress19/10 15:12 · Omar · 25s
In progress19/10 15:18 · Omar · 48s Robot inspectionDuct robot camera – exhaust riser9 min of riser footage (idle time removed from 10 min recorded)
All remaining photos and video clips for this room (4)
Sanitisation19/10 12:01 · OmarLabel on photo: Level 8 ISO 28
Sanitisation19/10 12:02 · OmarLabel on photo: Level 8 ISO 28
Before19/10 15:07 · OmarLabel on photo: level 8 before
In progress19/10 15:10 · Omar
Last room of the project, released by the ward in the evening. Fumigated 18:07, flexible duct cleaned and sprayed 18:28 – 18:54, room photographed after at 19:16. Daily report, 19 Oct: the room was fumigated and sanitised as soon as it was released, left for about 15 minutes, then cleaned. The exhaust-side filter opening was slightly damaged but could be opened. Both HEPA filters were removed, photographed and bagged (filter removal is outside the scope; it was done for the first and the last room on the timetable).
Sanitisation ✓Before ✓In progress ✓After ✓
Before
Before19/10 18:01 · OmarLabel on photo: 10A Iso 28 – room before
Before19/10 18:18 · Omardiffuser before After
After19/10 19:16 · Omarroom after Sanitisation and cleaning in progress
Sanitisation19/10 18:07 · Omar · 98s
In progress19/10 18:28 · Omar · 20s
In progress19/10 18:52 · Omar · 40s
In progress19/10 18:53 · Omar · 16s Robot inspectionDuct robot camera – exhaust riser14 min of riser footage (idle time removed from 34 min recorded)
All remaining photos and video clips for this room (2)
Before19/10 18:00 · OmarLabel on photo: 10A Iso 28 – room before
In progress19/10 18:50 · Omar · 43s