Completion report · Hospital Shah Alam (HSA) · Isolation rooms (negative pressure)

Duct cleaning and sanitisation of 21 isolation rooms

Supply (FCU) and exhaust air-duct cleaning, terminal sanitisation by fogging and bioactive duct treatment for the negative-pressure isolation rooms at Hospital Shah Alam, carried out over five weekly shutdown windows from 21 September to 19 October 2026 under the AWC shutdown schedule.

21isolation rooms completed
7working days
5weekly shutdown windows
171site photographs
164video clips · 86 min
Client / facility managerAmbang Wira Sdn Bhd (AWC Facilities)
Hospital Shah Alam, Persiaran Kayangan, Seksyen 7, 40000 Shah Alam
Carried out byOmar Zahid and Nor Syamir bin Nanwi (Padocx Exergy Sdn Bhd) with site crew Asif Usama and Hamayoun Mamoon
Scope referenceRFQ/AWSB/HSA/MEC/033 · Fumigation and disinfection, isolation rooms (negative pressure), 21 lots · AWC schedule 21/9/2026 – 23/10/2026
Report date22 October 2026
Scope and method

What was done in every room

Each isolation room has one fan-coil unit (FCU) supplying air through a flexible duct and ceiling diffuser, and an exhaust path through a floor-level louvre, an access panel and a riser that carries air up to the exhaust unit and its two HEPA filters. The same procedure was applied room by room. Rooms were sanitised first in batches, then cleaned one at a time.

  1. Terminal sanitisation (fogging)The sealed room is fogged with Bioactive Micro-Organism Surface Treatment (BMST, Airestec) using a ULV fogger, in full PPE.
  2. Supply / FCU sideThe ceiling diffuser is removed and washed. The flexible duct is brushed with a rotary drill brush and vacuumed (HEPA vacuum). With the FCU off, the duct is blown through with compressed air, then sprayed with Bioactive Micro-Organism Duct Treatment (BMDT) so the treatment reaches the FCU coil.
  3. Exhaust sideThe floor louvre and silicone-sealed access panel are removed. The plenum and riser are brush-cleaned, blown with compressed air and vacuumed. With the exhaust unit running, BMDT is sprayed in from the bottom so it is drawn up the riser.
  4. HEPA housing and riserWith both HEPA filters out and all units off, the duct robot is driven into the riser to blow compressed air as far as it reaches, followed by the air gun and BMDT spray. The robot's camera records the riser interior (footage in each room section).
  5. Close-outAll units are switched back on, a final BMDT spray is applied from the exhaust louvre, units are switched off, panels and louvres are washed, re-sealed with silicone and refitted. HEPA filter replacement and the air test are by the other appointed teams.

Equipment and consumables

Equipment01/10 12:16 · OmarDuct-cleaning robot (in-house build, 3D-printed body) used to drive into the exhaust riser behind the HEPA housing and blow compressed air.
Sanitisation22/09 11:50 · Omar · 26sULV fogger applying the bioactive surface treatment (BMST) during room sanitisation, full PPE.
In progress05/10 14:27 · Omar · 23sAir compressor set up outside the room; compressed air is fed to the duct through the access openings.
In progress05/10 10:48 · Omar · 17sIndustrial vacuum with HEPA filter and rotary brush drill for the flexible duct.
In progress05/10 12:31 · OmarRobot beside a removed HEPA filter at the exhaust unit, 9B ISO 27.
SDS22/09 09:59 · OmarSafety data sheet of the BMDT duct treatment solution kept on site.
Exhaust HEPA housing above the ceiling after cleaning: closed, re-sealed with foil tape and marked OK before the filters go back in.
Method · illustrated

How the duct robot cleans the exhaust riser

A schematic cross-section of one isolation room above the ceiling: the HEPA housing, the horizontal duct run and the riser down to the floor-level exhaust louvre. It walks through the sequence used in every room, from removing the filters to the two-sided BMDT treatment and re-sealing.

CEILING VOID ISOLATION ROOM (NEGATIVE PRESSURE) ROOM FLOOR RISER DUCT · FROM THE FLOOR LOUVRE UP TO THE HEPA HOUSING RISER · INSIDE THE WALL EXHAUST LOUVRE · ACCESS PANEL FLOOR LEVEL HEPA HOUSING · ROBOT ENTRY EXHAUST UNIT OFFPULLS AIR UP FROM THE LOUVRE AIR COMPRESSOR HEPA FILTERS REMOVED SETTLED DUST BMDT · BIOACTIVE DUCT TREATMENT ✓ RISER CLEANED AND TREATED EXHAUST RISER CLEANING · DUCT ROBOT · HSAS ISOLATION ROOMS · CROSS-SECTION 01 Prepare ROBOT CAM · RISER INTERIOR 00:00 Hospital Shah Alam · negative-pressure isolation rooms · 2026 How the duct robot cleans the exhaust riser Illustrated 2D animation · 10 steps · 56 s Riser cleaned and treated. Filters refitted. Housing sealed. Duct cleaning and sanitisation of 21 isolation rooms · Hospital Shah Alam Padocx Exergy Sdn Bhd · in-house duct robot

Ten steps, 56 seconds, then it repeats. Click the animation to pause and resume.

Room register

All 21 rooms by week

Each stage is ticked where the report holds a photograph; ✓v means the evidence is a still taken from site video. Room lists for weeks 2–5 are the client's shutdown notices; week 1 covers the five remaining rooms of the 21-room schedule.

WeekLevelWard / unitRoomSanitisedBeforeCleaningAfterPhotosClipsVideo
Week 1Level 4NICUISO 2✓v✓✓vpending814section
Week 1Level 5ICUISO 7pendingpendingpendingpending00section
Week 1Level 9Wad 9AISO 27✓v✓✓✓175section
Week 1Level 10Wad 10AISO 27✓v✓v✓✓32section
Week 1Level 12Pediatrik 12ISO 17pending✓✓v✓v45section
Week 2Level 9Wad 9AISO 28✓✓✓✓2213section
Week 2Level 5CCUISO 7✓✓✓✓1417section
Week 2Level 4NICUISO 1✓pending✓✓v49section
Week 2Level 5HDWISO 14✓✓v✓✓107section
Week 3Level 9Wad 9BISO 27✓✓✓✓1217section
Week 3Level 12Pediatrik 12ISO 18✓✓✓✓88section
Week 3Level 8O&G 8AISO 27✓✓✓v✓1112section
Week 3Level 8O&G 8AISO 28✓✓✓✓1112section
Week 4Level 11Ortopedik 11ISO 28pending✓v✓✓118section
Week 4Level 10Wad 10BISO 27pending✓✓✓53section
Week 4Level 9Wad 9BISO 28✓v✓✓✓68section
Week 4Level 8O&G 8BISO 27✓✓v✓✓68section
Week 5Level 11Ortopedik 11ISO 27✓✓✓✓v94section
Week 5Level 10Wad 10BISO 28✓✓✓v✓v73section
Week 5Level 8O&G 8BISO 28✓✓✓✓104section
Week 5Level 10Wad 10AISO 28✓v✓✓v✓45section

9 stages marked pending: the photo was not taken by this team on the day and has been requested from the site crew (see the list at the end of the report).

Week 1 of 5 · 5 rooms

Week 1

21 – 23 Sep 2026 (3 days)

Mobilisation week. Five rooms sanitised first, then cleaned over three days with work running into the night. HEPA filters for Level 4 were installed by the filter team on 24 Sep. Room numbers for this week come from the week-1 summary (Level 4 NICU, Level 5 ISO 7, Level 9, Level 10, Level 12) and the labels written on the photos.

Week 1 · Level 4

NICU (Neonatal Intensive Care Unit) ISO 2

21/09, 22/098 photos · 14 videos

First room of the project. Fumigated on 22 Sep morning (11:50 – 12:15), then the supply diffuser and flexible duct were opened, brush-cleaned and vacuumed. The completion photo was not taken on site and has been requested from the site team.

Sanitisation ✓Before ✓In progress ✓After · pending

Before

Before22/09 14:38 · OmarLabel on photo: NICU Level 4 Before
Before22/09 15:04 · OmarLabel on photo: INCU Before
Before21/09 16:19 · Omarsupply diffuser removed – dirty
Before22/09 14:30 · Omarflexible duct connection – dirty

After

Pending from site teamCompletion photo of the refitted diffuser / room

Sanitisation and cleaning in progress

Sanitisation22/09 11:50 · Omar · 26s
In progress22/09 15:05 · Omar · 32sdrill-brush cleaning of flexible duct
In progress22/09 15:08 · Omar · 17sdrill-brush cleaning of flexible duct
In progress21/09 16:46 · Omar · 39sceiling access / flexible duct
Site videoNICU (Neonatal Intensive Care Unit) ISO 2 – full site video (14 clips)Open video file
Robot inspection videoDuct robot camera footage – exhaust riserNo robot camera recording was matched to this room.
All remaining photos and video clips for this room (14)
Before21/09 11:24 · Omarsite survey – ceiling / pendant area
Before21/09 11:24 · Omarsite survey – ceiling / pendant area
In progress21/09 16:48 · Omar · 6sceiling access / flexible duct
Before21/09 19:08 · Omarroom overview with floor protection
Sanitisation22/09 11:50 · Omar · 40s
Sanitisation22/09 11:51 · Omar · 15s
Sanitisation22/09 11:52 · Omar · 7s
Sanitisation22/09 11:52 · Omar · 66s
Sanitisation22/09 11:54 · Omar · 11s
In progress22/09 14:30 · Omar · 27s
In progress22/09 14:33 · Omar · 21s
Before22/09 15:04 · OmarLabel on photo: INCU Before
In progress22/09 15:08 · Omar · 6sdrill-brush cleaning of flexible duct
In progress22/09 15:37 · Omar · 25sabove-ceiling view
Week 1 · Level 5

ICU (Intensive Care Unit) ISO 7

—0 photos · 0 videos

Recorded as completed in the week-1 summary (Level 5, ISO 7). No photographs were captured by this team; photos have been requested from the site team.

Sanitisation · pendingBefore · pendingIn progress · pendingAfter · pending

Before

Pending from site teamDiffuser / louvre before cleaning

After

Pending from site teamCompletion photo

Sanitisation and cleaning in progress

Pending from site teamFogging photo or video
Pending from site teamCleaning in progress
Robot inspectionDuct robot camera – exhaust riser10 min of riser footage (idle time removed from 34 min recorded)
Week 1 · Level 9

Wad Perubatan 9A ISO 27

22/09, 23/09, 25/0917 photos · 5 videos

Fumigated around 12:15 on 22 Sep. Supply side (two diffusers and flexible duct) and exhaust louvre documented before and after. Exhaust access panel re-sealed on 23 Sep; the ceiling opening at 9A was made good afterwards (25 Sep photos).

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before22/09 15:41 · OmarLabel on photo: Level 9 Before / Diffuser 1 & 2 Before
Before22/09 15:42 · OmarLabel on photo: Level 9 Before / Diffuser 1 & 2 Before
Before22/09 15:43 · OmarLabel on photo: Level 9 Before / Diffuser 1 & 2 Before
Before22/09 15:44 · Omar · 35sflexible duct – dirty

After

After22/09 17:03 · Omardiffusers washed
After23/09 16:46 · Omardiffusers cleaned / reinstalled
After23/09 16:48 · Omardiffusers cleaned / reinstalled
After23/09 19:58 · Omarexhaust access panel sealed

Sanitisation and cleaning in progress

Sanitisation22/09 12:15 · Omar · 25s
In progress22/09 15:50 · Omar · 16s
In progress22/09 15:54 · Omar · 15s
After25/09 12:31 · Syamirceiling make-good at 9A
Site videoWad Perubatan 9A ISO 27 – full site video (5 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser9 min of riser footage (idle time removed from 15 min recorded)
All remaining photos and video clips for this room (10)
Before22/09 15:41 · OmarLabel on photo: Level 9 Before / Diffuser 1 & 2 Before
Before22/09 15:41 · OmarLabel on photo: Level 9 Before / Diffuser 1 & 2 Before
Before22/09 15:43 · OmarLabel on photo: Level 9 Before / Diffuser 1 & 2 Before
In progress22/09 17:03 · Omar · 5s
In progress22/09 17:10 · Omarabove ceiling
After23/09 16:49 · Omardiffusers cleaned / reinstalled
After23/09 18:40 · Omardiffuser reinstalled
After23/09 19:58 · Omarexhaust access panel sealed
In progress23/09 20:57 · Omarduct interior
After25/09 12:31 · Syamirceiling make-good at 9A
Week 1 · Level 10

Wad Perubatan 10A ISO 27

22/09, 23/093 photos · 2 videos

Fumigated on 22 Sep at 12:35 (the room frame before fogging is taken from that video); exhaust access panel cleaned and re-sealed on the night of 23 Sep. Live-streamed during the night shift.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before22/09 12:35 · OmarRoom prior to sanitisation (frame at 2s of site video)

After

After23/09 23:32 · OmarLabel on photo: level 10 Isolation 27 – exhaust access panel

Sanitisation and cleaning in progress

Sanitisation22/09 12:35 · Omar · 70s
Sanitisation22/09 12:36 · Omar · 47s
In progress23/09 23:32 · Omarexhaust access panel opened for cleaning
Site videoWad Perubatan 10A ISO 27 – full site video (2 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser13 min of riser footage (idle time removed from 44 min recorded)
Week 1 · Level 12

Wad Pediatrik 12 ISO 17

23/09, 24/094 photos · 5 videos

Ceiling openings and flexible duct photographed before cleaning on 23 Sep evening; BMDT treatment applied to the cleaned flexible duct at 23:06; exhaust grille work continued past midnight into 24 Sep. The fogging of this room was not filmed.

Sanitisation · pendingBefore ✓In progress ✓After ✓

Before

Before23/09 19:07 · OmarLabel on photo: Level 12 Isolasi 17
Before23/09 19:06 · Omarceiling opening / flexible duct
Before23/09 19:06 · Omarceiling opening / flexible duct

After

After23/09 23:06 · OmarBMDT duct treatment applied after cleaning (FCU side) (frame at 10s of site video)

Sanitisation and cleaning in progress

In progress23/09 23:01 · Omar · 27sexhaust-side work
In progress23/09 23:02 · Omar · 32sexhaust-side work
In progress23/09 23:06 · Omar · 23sexhaust-side work
In progress24/09 00:04 · Omar · 9sexhaust grille work, after midnight
Pending from site teamFogging photo or video
Site videoWad Pediatrik 12 ISO 17 – full site video (5 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser10 min of riser footage (idle time removed from 42 min recorded) · room attribution to be confirmed
All remaining photos and video clips for this room (1)
In progress23/09 23:02 · Omar · 8sexhaust-side work
Week 2 of 5 · 4 rooms

Week 2

Mon 28 Sep 2026

Four rooms in one shift (10:40 to about 21:30). Two teams worked in parallel: Omar on Level 9 then Level 5 (CCU, HDW); the second team took the before/after set on Level 9 and worked the remaining rooms.

Week 2 · Level 9

Wad Perubatan 9A ISO 28

28/0922 photos · 13 videos

Best-documented room: fumigation, a full before/after set of the diffuser and both louvres from the second team, and the exhaust duct interior after compressed-air cleaning.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before28/09 12:42 · HamayounBefore
Before28/09 13:37 · HamayounBefore
Before28/09 13:43 · HamayounBefore
Before28/09 13:43 · HamayounBefore

After

After28/09 13:37 · HamayounAfter
After28/09 13:39 · HamayounAfter
After28/09 13:43 · HamayounAfter
After28/09 13:19 · OmarLabel on photo: level 9 after

Sanitisation and cleaning in progress

Sanitisation28/09 10:39 · Omar
Sanitisation28/09 10:42 · Omar · 75s
In progress28/09 13:13 · Omar · 104scompressed air / brush in exhaust duct
After28/09 13:27 · Omarexhaust duct interior after cleaning
Site videoWad Perubatan 9A ISO 28 – full site video (13 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser13 min of riser footage (idle time removed from 43 min recorded) · room attribution to be confirmed
All remaining photos and video clips for this room (23)
Sanitisation28/09 10:40 · Omar
Sanitisation28/09 10:45 · Omar · 41s
In progress28/09 12:52 · Hamayoun
In progress28/09 12:52 · Hamayoun · 16s
In progress28/09 13:10 · Omar · 4scompressed air / brush in exhaust duct
In progress28/09 13:10 · Omar · 12scompressed air / brush in exhaust duct
In progress28/09 13:12 · Omar · 16scompressed air / brush in exhaust duct
After28/09 13:18 · OmarLabel on photo: level 9 after
After28/09 13:18 · OmarLabel on photo: level 9 after
After28/09 13:28 · Omarexhaust duct interior after cleaning
After28/09 13:29 · Omar · 4sexhaust duct interior after cleaning
After28/09 13:30 · Omar · 16sexhaust duct interior after cleaning
After28/09 13:30 · Omar · 20sexhaust duct interior after cleaning
After28/09 13:31 · Omar · 7sexhaust duct interior after cleaning
After28/09 13:31 · Omar · 10sexhaust duct interior after cleaning
Before28/09 13:37 · HamayounBefore
In progress28/09 13:37 · Hamayoun
After28/09 13:39 · HamayounAfter
After28/09 13:43 · HamayounAfter
In progress28/09 13:48 · Omarcompressor set-up in corridor
After28/09 21:21 · Omarexhaust access panel sealed
After28/09 21:21 · Omarexhaust access panel sealed
After28/09 21:21 · Omar · 12sexhaust access panel sealed
Week 2 · Level 5

CCU (Coronary Care Unit) ISO 7

28/0914 photos · 17 videos

Fumigated 10:56 – 11:00 (the "Isolasi 7" door sign is visible in the video). Full sequence: dirty diffuser, louvres and duct interior before; compressed-air and vacuum work; BMDT spray; diffuser and louvres refitted after.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before28/09 16:00 · OmarLabel on photo: Level 5 CCU ISO 7 Before
Before28/09 15:57 · OmarLabel on photo: Level 5 CCU ISO 7 Before
Before28/09 15:57 · OmarLabel on photo: Level 5 CCU ISO 7 Before
Before28/09 15:59 · OmarLabel on photo: Level 5 CCU ISO 7 Before

After

After28/09 16:34 · OmarLabel on photo: After CCU Level 5
After28/09 16:36 · OmarLabel on photo: After CCU Level 5
After28/09 16:36 · OmarLabel on photo: After CCU Level 5

Sanitisation and cleaning in progress

Sanitisation28/09 10:58 · Omar · 36sdoor sign "Isolasi 7" visible in the 10:58 video
In progress28/09 16:09 · Omar · 42s
In progress28/09 16:25 · Omar · 36s
In progress28/09 16:27 · Omar · 21s
Site videoCCU (Coronary Care Unit) ISO 7 – full site video (17 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser6 min of riser footage (idle time removed from 24 min recorded)
All remaining photos and video clips for this room (20)
Sanitisation28/09 10:55 · Omardoor sign "Isolasi 7" visible in the 10:58 video
Sanitisation28/09 10:56 · Omar · 83sdoor sign "Isolasi 7" visible in the 10:58 video
Sanitisation28/09 11:00 · Omar · 1sdoor sign "Isolasi 7" visible in the 10:58 video
In progress28/09 15:34 · Omar · 33sabove ceiling
Before28/09 15:57 · OmarLabel on photo: Level 5 CCU ISO 7 Before
Before28/09 15:57 · OmarLabel on photo: Level 5 CCU ISO 7 Before
Before28/09 15:58 · OmarLabel on photo: Level 5 CCU ISO 7 Before
Before28/09 15:58 · OmarLabel on photo: Level 5 CCU ISO 7 Before
Before28/09 15:59 · Omar · 9sLabel on photo: Level 5 CCU ISO 7 Before
In progress28/09 16:01 · Omar · 9s
In progress28/09 16:01 · Omar · 14s
In progress28/09 16:02 · Omar · 30s
In progress28/09 16:07 · Omar · 30s
In progress28/09 16:10 · Omar · 53s
In progress28/09 16:19 · Omar · 49s
In progress28/09 16:20 · Omar · 18s
In progress28/09 16:29 · Omar · 20s
In progress28/09 16:31 · Omar · 9s
In progress28/09 16:31 · Omar
After28/09 16:33 · OmarLabel on photo: After CCU Level 5
Week 2 · Level 4

NICU (Neonatal Intensive Care Unit) ISO 1

28/094 photos · 9 videos

Fumigated 11:12 – 11:17 (labelled photo). Cleaning was carried out by the second team; their evening set shows the flexible-duct brushing, exhaust panel work and the final BMDT spray at the louvre. A before photo has been requested from the site team.

Sanitisation ✓Before · pendingIn progress ✓After ✓

Before

Pending from site teamDiffuser / louvre before cleaning

After

After28/09 20:21 · HamayounFinal BMDT spray at the exhaust louvre (close-out) (frame at 3s of site video)

Sanitisation and cleaning in progress

Sanitisation28/09 11:16 · OmarLabel on photo: NICU Level 4 Isolation 1
Sanitisation28/09 11:13 · Omar · 23sLabel on photo: NICU Level 4 Isolation 1
In progress28/09 20:20 · Hamayoun
In progress28/09 20:21 · Hamayoun · 33s
Site videoNICU (Neonatal Intensive Care Unit) ISO 1 – full site video (9 clips)Open video file
Robot inspection videoDuct robot camera footage – exhaust riserOne recording from 28 Sep 20:44 may belong to this room or to 9A ISO 28; it is shown under 9A ISO 28 until confirmed.
All remaining photos and video clips for this room (8)
Sanitisation28/09 11:12 · OmarLabel on photo: NICU Level 4 Isolation 1
Sanitisation28/09 11:15 · Omar · 27sLabel on photo: NICU Level 4 Isolation 1
In progress28/09 20:21 · Hamayoun · 15s
In progress28/09 20:21 · Hamayoun · 9s
In progress28/09 20:21 · Hamayoun · 9s
In progress28/09 20:21 · Hamayoun · 26s
In progress28/09 20:21 · Hamayoun · 14s
In progress28/09 20:21 · Hamayoun · 18s
Week 2 · Level 5

HDW (High Dependency Ward) ISO 14

28/0910 photos · 7 videos

Fumigated 11:20 – 11:27; exhaust plenum and HEPA housing cleaned in the late afternoon, FCU flexible duct brushed and vacuumed, diffuser and louvre refitted (labelled after photo 17:59).

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before28/09 16:59 · OmarExhaust plenum interior before cleaning (frame at 1s of site video)
Before28/09 17:59 · OmarFCU flexible duct at start of brushing (frame at 49s of site video)

After

After28/09 17:59 · OmarLabel on photo: HDW14 Level 5 After
After28/09 17:59 · OmarLabel on photo: HDW14 Level 5 After

Sanitisation and cleaning in progress

Sanitisation28/09 11:20 · OmarLabel on photo: HDW 14 Level 5
Sanitisation28/09 11:21 · Omar · 89sLabel on photo: HDW 14 Level 5
In progress28/09 17:59 · Omar · 66sFCU flexible duct cleaning + BMDT spray
In progress28/09 18:13 · Omar · 27sFCU flexible duct cleaning + BMDT spray
Site videoHDW (High Dependency Ward) ISO 14 – full site video (7 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser32 min of riser footage (idle time removed from 78 min recorded)
All remaining photos and video clips for this room (9)
Sanitisation28/09 11:20 · OmarLabel on photo: HDW 14 Level 5
Sanitisation28/09 11:21 · OmarLabel on photo: HDW 14 Level 5
Sanitisation28/09 11:21 · OmarLabel on photo: HDW 14 Level 5
Sanitisation28/09 11:27 · Omar · 7sLabel on photo: HDW 14 Level 5
Sanitisation28/09 11:27 · Omar · 19sLabel on photo: HDW 14 Level 5
In progress28/09 16:58 · Omarexhaust duct / HEPA housing
In progress28/09 16:59 · Omar · 25sexhaust duct / HEPA housing
In progress28/09 17:03 · Omar · 19sexhaust duct / HEPA housing
After28/09 17:59 · OmarLabel on photo: HDW14 Level 5 After
Week 3 of 5 · 4 rooms

Week 3

Mon 5 Oct 2026

Four rooms: both 8A isolation rooms on Level 8, 9B ISO 27 on Level 9 and the Level 12 paediatric room ISO 18. The FCU above 8A ISO 28 showed the heaviest fouling of the project. The duct robot was used in the exhaust riser at 9B.

Daily report · 5 October 2026 · dictated on site by Omar
  • Construction and cleaning work was still under way in Ward 8A, so the day began by tidying the rooms and vacuuming the floors.
  • Sanitisation (fogging) completed on Level 8 (both 8A rooms), Level 12 and Level 9.
  • 8A ISO 28: exhaust side cleaned from the floor opening. FCU side cleaned, including the flexible ducting and covers on the bathroom side and outside the room; sanitisation spray applied to the flexible ducting (filmed).
  • Inspection found significant condensation on the main FCU duct in 8A ISO 28. That section has no opening or cover; a video records the condition.
  • The ceiling in 8A ISO 28 is in poor condition. Ceiling repair is outside the scope of this work. The layout is otherwise the same as ISO 27.
Week 3 · Level 9

Wad Perubatan 9B ISO 27

05/1012 photos · 17 videos

Exhaust plenum sprayed and brushed, duct interior photographed before, diffusers and louvres refitted after. The duct-cleaning robot and a removed HEPA filter are visible in the 12:31 photo.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before05/10 11:52 · Omarexhaust duct interior – before

After

After05/10 12:52 · Omardiffusers and louvre refitted
After05/10 17:53 · Omarexhaust louvres refitted
After05/10 17:58 · Omarexhaust louvres refitted
After05/10 17:59 · Omarexhaust louvres refitted

Sanitisation and cleaning in progress

Sanitisation05/10 11:21 · Omardoor sign Iso27, Level 9 floor
Sanitisation05/10 11:23 · Omar · 84sdoor sign Iso27, Level 9 floor
In progress05/10 11:58 · Omar · 24s
In progress05/10 12:31 · Omar
Site videoWad Perubatan 9B ISO 27 – full site video (17 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser18 min of riser footage (idle time removed from 37 min recorded)
All remaining photos and video clips for this room (20)
Sanitisation05/10 11:22 · Omardoor sign Iso27, Level 9 floor
In progress05/10 11:49 · Omar · 2sexhaust access panel – BMDT spray
In progress05/10 11:49 · Omar · 21sexhaust access panel – BMDT spray
In progress05/10 11:50 · Omar · 75sexhaust access panel – BMDT spray
In progress05/10 11:54 · Omar · 36s
In progress05/10 11:59 · Omar
In progress05/10 12:04 · Omar · 30s
In progress05/10 12:08 · Omar · 36s
In progress05/10 12:11 · Omar · 3s
In progress05/10 12:12 · Omar
In progress05/10 12:26 · Omar · 8s
In progress05/10 12:28 · Omar
In progress05/10 12:46 · Omar · 46sFCU flexible duct vacuum
After05/10 12:53 · Omar · 5sdiffusers and louvre refitted
After05/10 12:54 · Omar · 8sdiffusers and louvre refitted
In progress05/10 17:43 · Omar · 29sexhaust side – BMDT spray / door Iso27
In progress05/10 17:46 · Omarexhaust side – BMDT spray / door Iso27
In progress05/10 17:46 · Omarexhaust side – BMDT spray / door Iso27
In progress05/10 17:47 · Omar · 85sexhaust side – BMDT spray / door Iso27
After05/10 17:53 · Omar · 14sexhaust louvres refitted
Week 3 · Level 12

Wad Pediatrik 12 ISO 18

05/108 photos · 8 videos

FCU above the ceiling photographed before (labelled), flexible duct vacuumed, diffusers and louvre refitted after. Sanitised on the morning of 5 Oct together with Level 8 and Level 9.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before05/10 16:08 · OmarLabel on photo: Level 12 Isolasi 18
Before05/10 16:06 · OmarFCU above ceiling
In progress05/10 15:40 · Omaryellow floor = Level 12

After

After05/10 16:56 · Omardiffusers + louvre refitted
After05/10 16:56 · Omardiffusers + louvre refitted
After05/10 16:56 · Omardiffusers + louvre refitted

Sanitisation and cleaning in progress

Sanitisation05/10 11:16 · Omar · 74syellow floor = Level 12
In progress05/10 16:12 · Omar · 29s
In progress05/10 16:47 · Omar · 13s
Site videoWad Pediatrik 12 ISO 18 – full site video (8 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser17 min of riser footage (idle time removed from 24 min recorded)
All remaining photos and video clips for this room (7)
Sanitisation05/10 11:12 · Omar · 1syellow floor = Level 12
Sanitisation05/10 11:12 · Omaryellow floor = Level 12
Sanitisation05/10 11:14 · Omaryellow floor = Level 12
In progress05/10 15:43 · Omar · 6syellow floor = Level 12
In progress05/10 15:46 · Omar · 36syellow floor = Level 12
Before05/10 16:05 · Omar · 17sFCU above ceiling
In progress05/10 16:21 · Omar · 4s
Week 3 · Level 8

Wad Obstetrik & Ginekologi 8A ISO 27

28/09, 05/1011 photos · 12 videos

Fumigated on 28 Sep and again on 5 Oct morning (labelled "8A no 27"). Before/after set of the diffuser and louvres from the second team on 5 Oct.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before05/10 13:38 · HamayounBefore
Before05/10 13:38 · HamayounBefore
Before05/10 13:38 · HamayounBefore
Before05/10 13:38 · HamayounBefore

After

After05/10 13:38 · HamayounAfter
After05/10 13:38 · HamayounAfter

Sanitisation and cleaning in progress

Sanitisation05/10 11:00 · OmarLabel on photo: 8A no 27
Sanitisation05/10 11:00 · Omar · 73sLabel on photo: 8A no 27
In progress05/10 13:38 · Hamayoun · 19s
In progress05/10 18:23 · Omar · 51sHEPA housing / ceiling flex
Site videoWad Obstetrik & Ginekologi 8A ISO 27 – full site video (12 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser14 min of riser footage (idle time removed from 16 min recorded)
All remaining photos and video clips for this room (13)
Sanitisation28/09 11:05 · Omarannotated by Omar as 8A ISO 27
Sanitisation28/09 11:05 · Omarannotated by Omar as 8A ISO 27
In progress05/10 10:48 · Omar · 17sequipment set-up
Sanitisation05/10 10:59 · OmarLabel on photo: 8A no 27
Sanitisation05/10 11:02 · Omar · 20sLabel on photo: 8A no 27
In progress05/10 13:38 · Hamayoun · 7s
Before05/10 13:39 · HamayounBefore
In progress05/10 13:39 · Hamayoun · 24s
In progress05/10 13:39 · Hamayoun · 27s
In progress05/10 13:39 · Hamayoun · 35s
In progress05/10 18:25 · Omar · 30sHEPA housing / ceiling flex
In progress05/10 18:31 · Omar · 5sHEPA housing / ceiling flex
In progress05/10 18:31 · Omar · 9sHEPA housing / ceiling flex
Week 3 · Level 8

Wad Obstetrik & Ginekologi 8A ISO 28

05/1011 photos · 12 videos

Heaviest fouling found in the project: the FCU drain pan and casing above the ceiling were coated in biofilm. Flexible duct, exhaust plenum and louvres cleaned; diffuser refitted. Daily report, 5 Oct: exhaust side cleaned from the floor opening; FCU side cleaned including the flexible ducting and covers on the bathroom side and outside the room, with sanitisation spray applied to the flexible ducting. Significant condensation was found on the main FCU duct, which has no opening or cover (filmed). The ceiling of this room is in poor condition; ceiling work is outside this scope.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before05/10 14:16 · OmarLabel on photo: 8A - no 28 – flexible duct dirty
Before05/10 14:46 · OmarFCU unit above ceiling – heavy fouling
Before05/10 14:46 · OmarFCU unit above ceiling – heavy fouling
Before05/10 14:46 · OmarFCU unit above ceiling – heavy fouling

After

After05/10 14:39 · Omardiffuser refitted
After05/10 15:37 · Omardiffuser refitted

Sanitisation and cleaning in progress

Sanitisation05/10 11:05 · Omaradjacent 8A room
In progress05/10 14:18 · Omar · 51s
In progress05/10 14:27 · Omar · 23s
In progress05/10 14:38 · Omar · 6s
Site videoWad Obstetrik & Ginekologi 8A ISO 28 – full site video (12 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser15 min of riser footage (idle time removed from 32 min recorded)
All remaining photos and video clips for this room (13)
Sanitisation05/10 11:06 · Omar · 57sadjacent 8A room
Sanitisation05/10 11:07 · Omar · 22sadjacent 8A room
Before05/10 14:15 · OmarLabel on photo: 8A - no 28 – flexible duct dirty
Before05/10 14:15 · OmarLabel on photo: 8A - no 28 – flexible duct dirty
In progress05/10 14:21 · Omar · 36s
In progress05/10 14:24 · Omar · 40s
In progress05/10 14:27 · Omar · 431s
In progress05/10 14:35 · Omar · 13s
In progress05/10 14:41 · Omarexhaust access panel
Before05/10 14:45 · Omar · 51sFCU unit above ceiling – heavy fouling
In progress05/10 14:58 · Omarwaste bagged
In progress05/10 15:16 · Omar · 4s
In progress05/10 15:18 · Omar · 18s
Week 4 of 5 · 4 rooms

Week 4

Mon 12 Oct 2026

Four rooms across Levels 8 to 11. Omar completed 11 ISO 28 and 10B ISO 27; the second team covered 8B ISO 27 and 9B ISO 28 and sent their photo sets at 13:34, 17:52 and 18:08.

Daily report · 12 October 2026 · dictated on site by Omar
  • Omar arrived late and missed the fumigation of the first two rooms; he joined the team for the fumigation of 9B ISO 28 and then 8B ISO 27.
  • After lunch the team continued on Level 11 (ISO 28): FCU side and exhaust side completed, including the robot camera run.
  • 10B ISO 27: the FCU-side ceiling opening was obstructed by formwork. The team reached the area from the adjacent staff room / pantry by climbing onto a beam and crossing over; no formwork was cut or removed. The robot was inserted from the other side and the cleaning completed with the normal procedure. This room was first reported as 9B and corrected to 10B.
  • 9B ISO 28 and 8B ISO 27: exhaust side and FCU cleaned with the usual procedure; set-up similar to the previous rooms. An odour was noticed in 8B ISO 27.
Week 4 · Level 11

Wad Ortopedik 11 ISO 28

12/1011 photos · 8 videos

Second team cleaned this room (flexible duct brushing from the ladder, louvres and plenum); Omar's labelled room photo marks completion at 15:58. Fogging was not filmed. Daily report, 12 Oct: FCU side and exhaust side completed after lunch, including the robot camera run.

Sanitisation · pendingBefore ✓In progress ✓After ✓

Before

Before12/10 13:35 · HamayounFlexible duct before cleaning (frame at 1s of site video)
Before12/10 13:35 · HamayounFlexible duct before cleaning (frame at 1s of site video)

After

After12/10 15:58 · OmarLabel on photo: Level 11 - ISO 28 After
After12/10 15:57 · OmarLabel on photo: Level 11 - ISO 28 After

Sanitisation and cleaning in progress

In progress12/10 13:34 · Hamayoun
In progress12/10 13:34 · Hamayoun
In progress12/10 13:35 · Hamayoun
In progress12/10 13:35 · Hamayoun · 13s
Pending from site teamFogging photo or video
Site videoWad Ortopedik 11 ISO 28 – full site video (8 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser15 min of riser footage (idle time removed from 20 min recorded)
All remaining photos and video clips for this room (11)
In progress12/10 13:34 · Hamayoun · 2s
In progress12/10 13:34 · Hamayoun · 15s
In progress12/10 13:35 · Hamayoun
In progress12/10 13:35 · Hamayoun
In progress12/10 13:35 · Hamayoun
In progress12/10 13:35 · Hamayoun · 7s
In progress12/10 13:35 · Hamayoun · 8s
In progress12/10 13:35 · Hamayoun · 20s
In progress12/10 13:35 · Hamayoun · 31s
In progress12/10 13:35 · Hamayoun · 64s
After12/10 15:57 · OmarLabel on photo: Level 11 - ISO 28 After
Week 4 · Level 10

Wad Perubatan 10B ISO 27

12/105 photos · 3 videos

Exhaust louvre photographed dirty at 16:12, plenum cleaned above the ceiling, room photographed after completion (labelled 17:26). Fogging was not filmed. Daily report, 12 Oct: the FCU-side ceiling opening was obstructed by formwork; the team reached it from the adjacent staff room / pantry by climbing onto a beam and crossing over (no formwork was cut or removed). The robot was inserted from the other side and the cleaning completed with the normal procedure. The room was first reported as 9B and corrected to 10B.

Sanitisation · pendingBefore ✓In progress ✓After ✓

Before

Before12/10 16:12 · Omarexhaust louvre before cleaning – dust on blades

After

After12/10 17:26 · OmarLabel on photo: Level 10 B ISO 27 After
After12/10 17:26 · OmarLabel on photo: Level 10 B ISO 27 After

Sanitisation and cleaning in progress

In progress12/10 16:31 · Omar
In progress12/10 16:45 · Omar · 18s
In progress12/10 17:19 · Omar
Pending from site teamFogging photo or video
Site videoWad Perubatan 10B ISO 27 – full site video (3 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser9 min of riser footage (idle time removed from 14 min recorded)
All remaining photos and video clips for this room (2)
In progress12/10 16:25 · Omar · 18s
In progress12/10 16:35 · Omar · 2s
Week 4 · Level 9

Wad Perubatan 9B ISO 28

12/106 photos · 8 videos

Fumigated at 12:55; cleaned by the second team in the evening: louvre photographed before, plenum brushed and vacuumed, louvres refitted after (18:08), final duct work by Omar at 19:09. Daily report, 12 Oct: Omar arrived late and joined the team for the fumigation of this room, then 8B ISO 27; the exhaust side and FCU were cleaned with the usual procedure.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before12/10 18:08 · HamayounExhaust louvre before cleaning – dust on blades

After

After12/10 18:08 · HamayounLouvre refitted after cleaning
After12/10 18:08 · HamayounLouvre refitted after cleaning
After12/10 18:08 · HamayounLouvre refitted after cleaning

Sanitisation and cleaning in progress

Sanitisation12/10 12:55 · Omar · 52sLevel 9 floor
In progress12/10 18:08 · Hamayoun · 28s
In progress12/10 18:09 · Hamayoun · 27s
In progress12/10 19:09 · Omarevening work
Site videoWad Perubatan 9B ISO 28 – full site video (8 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser8 min of riser footage (idle time removed from 12 min recorded) · room attribution to be confirmed
All remaining photos and video clips for this room (6)
Sanitisation12/10 12:57 · Omar · 34sLevel 9 floor
In progress12/10 18:09 · Hamayoun · 30s
In progress12/10 18:09 · Hamayoun · 17s
In progress12/10 18:10 · Hamayoun
In progress12/10 19:11 · Omar · 246sevening work
In progress12/10 19:19 · Omar · 10sevening work
Week 4 · Level 8

Wad Obstetrik & Ginekologi 8B ISO 27

12/106 photos · 8 videos

Fumigated 13:05 (labelled). Second team cleaned the flexible duct and plenum (17:52) and finished with the BMDT spray at the refitted exhaust louvre. Daily report, 12 Oct: exhaust side and FCU cleaned with the usual procedure, set-up similar to the previous rooms. An odour was noticed in this room.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before12/10 13:06 · OmarRoom prior to sanitisation (frame at 2s of site video)

After

After12/10 17:52 · HamayounFinal BMDT spray at the refitted exhaust louvre (close-out)

Sanitisation and cleaning in progress

Sanitisation12/10 13:05 · OmarLabel on photo: 8B ISO 27
Sanitisation12/10 13:06 · Omar · 72sLabel on photo: 8B ISO 27
In progress12/10 17:52 · Hamayoun
In progress12/10 17:52 · Hamayoun · 15s
Site videoWad Obstetrik & Ginekologi 8B ISO 27 – full site video (8 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser10 min of riser footage (idle time removed from 17 min recorded) · room attribution to be confirmed
All remaining photos and video clips for this room (8)
Sanitisation12/10 13:05 · OmarLabel on photo: 8B ISO 27
Sanitisation12/10 13:07 · Omar · 31sLabel on photo: 8B ISO 27
Sanitisation12/10 13:09 · OmarLabel on photo: 8B ISO 27
In progress12/10 17:52 · Hamayoun · 13s
In progress12/10 17:52 · Hamayoun · 16s
In progress12/10 17:52 · Hamayoun · 13s
In progress12/10 17:52 · Hamayoun · 9s
In progress12/10 17:52 · Hamayoun · 12s
Week 5 of 5 · 4 rooms

Week 5

Mon 19 Oct 2026

Final four rooms. 10A ISO 28 was still occupied in the morning, so the other three rooms were fumigated first (11:34 – 12:03) and 10A was handed over and completed in the evening (18:00 – 19:16), closing out all 21 rooms.

Daily report · 19 October 2026 · dictated on site by Omar
  • Started on Level 11 (ISO 27). 10A ISO 28 was still occupied, so the team moved to Level 8 (8B ISO 28) and then 10B ISO 28. 10A was fumigated as soon as it was released, left for about 15 minutes, then cleaned.
  • Level 11 ISO 27: water was found dripping onto the floor. Possible sources are a square tank on the roof and the FCU side when the ceiling cover was opened. The source was not confirmed; the FCU (air-conditioning) side still needs to be checked.
  • 8B ISO 28: usual work completed. FCU in good condition, no leaks, generally clean.
  • 10B ISO 28: usual work completed. The exhaust filter housing sits outside the room, unlike the other rooms, so the team climbed the wall to reach it. Clear robot video recorded.
  • 10A ISO 28: the exhaust-side filter opening was slightly damaged but could be opened. Both HEPA filters were removed, photographed and bagged. Filter removal is outside the scope; it was done for the first and the last room on the timetable.
Week 5 · Level 11

Wad Ortopedik 11 ISO 27

19/109 photos · 4 videos

Fumigated 11:34, dirty flexible duct labelled "Before" at 11:42; plenum and diffuser cleaned 14:33 – 14:39 and finished with the BMDT spray at the refitted louvre. Daily report, 19 Oct: water was found dripping onto the floor (possible sources: a square tank on the roof, or the FCU side when the ceiling cover was opened); the source was not confirmed. The report left this room's completion open, but the photo record shows the plenum, diffuser and louvre finished at 14:33 – 14:39.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before19/10 11:42 · OmarLabel on photo: Level 11 iso 27 Before
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before

After

After19/10 14:33 · OmarFinal BMDT spray at the refitted exhaust louvre (frame at 1s of site video)

Sanitisation and cleaning in progress

Sanitisation19/10 11:34 · Omar
Sanitisation19/10 11:34 · Omar · 92s
In progress19/10 14:33 · Omar · 8s
In progress19/10 14:35 · Omar · 11s
Site videoWad Ortopedik 11 ISO 27 – full site video (4 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser9 min of riser footage (idle time removed from 24 min recorded)
All remaining photos and video clips for this room (5)
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before
Before19/10 11:41 · OmarLabel on photo: Level 11 iso 27 Before
In progress19/10 14:37 · Omar
In progress19/10 14:37 · Omar
In progress19/10 14:39 · Omar · 39s
Week 5 · Level 10

Wad Perubatan 10B ISO 28

19/107 photos · 3 videos

Fumigated 11:52 (labelled room photo); dirty diffuser labelled "Before" 16:03; flexible duct cleaned and treated with BMDT 16:09 – 16:45. Daily report, 19 Oct: the exhaust filter housing sits outside the room, unlike the other rooms, so the team climbed the wall to reach it. Clear robot video recorded.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before19/10 16:03 · OmarLabel on photo: 10 B Before
Before19/10 16:03 · OmarLabel on photo: 10 B Before

After

After19/10 16:45 · OmarBMDT treatment applied to the flexible duct after cleaning (frame at 14s of site video)
After19/10 16:45 · OmarBMDT treatment applied to the flexible duct after cleaning (frame at 20s of site video)

Sanitisation and cleaning in progress

Sanitisation19/10 11:51 · OmarLabel on photo: 10B Iso 28
Sanitisation19/10 11:52 · Omar · 54sLabel on photo: 10B Iso 28
In progress19/10 16:09 · Omar · 19s
In progress19/10 16:45 · Omar · 21s
Site videoWad Perubatan 10B ISO 28 – full site video (3 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser14 min of riser footage (idle time removed from 20 min recorded)
All remaining photos and video clips for this room (2)
Sanitisation19/10 11:50 · OmarLabel on photo: 10B Iso 28
Before19/10 16:03 · OmarLabel on photo: 10 B Before
Week 5 · Level 8

Wad Obstetrik & Ginekologi 8B ISO 28

19/1010 photos · 4 videos

Full sequence with labelled before (15:07) and after (15:56) room and diffuser photos; exhaust plenum cleaned 15:10 – 15:18. Daily report, 19 Oct: FCU in good condition, no leaking, generally clean.

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before19/10 15:08 · OmarLabel on photo: level 8 before
Before19/10 15:07 · OmarLabel on photo: level 8 before
In progress19/10 15:10 · Omar
In progress19/10 15:10 · Omar

After

After19/10 15:56 · OmarLabel on photo: level 8 after
After19/10 15:56 · OmarLabel on photo: level 8 after

Sanitisation and cleaning in progress

Sanitisation19/10 12:01 · OmarLabel on photo: Level 8 ISO 28
Sanitisation19/10 12:02 · Omar · 65sLabel on photo: Level 8 ISO 28
In progress19/10 15:12 · Omar · 25s
In progress19/10 15:18 · Omar · 48s
Site videoWad Obstetrik & Ginekologi 8B ISO 28 – full site video (4 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser9 min of riser footage (idle time removed from 10 min recorded)
All remaining photos and video clips for this room (4)
Sanitisation19/10 12:01 · OmarLabel on photo: Level 8 ISO 28
Sanitisation19/10 12:02 · OmarLabel on photo: Level 8 ISO 28
Before19/10 15:07 · OmarLabel on photo: level 8 before
In progress19/10 15:10 · Omar
Week 5 · Level 10

Wad Perubatan 10A ISO 28

19/104 photos · 5 videos

Last room of the project, released by the ward in the evening. Fumigated 18:07, flexible duct cleaned and sprayed 18:28 – 18:54, room photographed after at 19:16. Daily report, 19 Oct: the room was fumigated and sanitised as soon as it was released, left for about 15 minutes, then cleaned. The exhaust-side filter opening was slightly damaged but could be opened. Both HEPA filters were removed, photographed and bagged (filter removal is outside the scope; it was done for the first and the last room on the timetable).

Sanitisation ✓Before ✓In progress ✓After ✓

Before

Before19/10 18:01 · OmarLabel on photo: 10A Iso 28 – room before
Before19/10 18:18 · Omardiffuser before

After

After19/10 19:16 · Omarroom after

Sanitisation and cleaning in progress

Sanitisation19/10 18:07 · Omar · 98s
In progress19/10 18:28 · Omar · 20s
In progress19/10 18:52 · Omar · 40s
In progress19/10 18:53 · Omar · 16s
Site videoWad Perubatan 10A ISO 28 – full site video (5 clips)Open video file
Robot inspectionDuct robot camera – exhaust riser14 min of riser footage (idle time removed from 34 min recorded)
All remaining photos and video clips for this room (2)
Before19/10 18:00 · OmarLabel on photo: 10A Iso 28 – room before
In progress19/10 18:50 · Omar · 43s
Site observations

Findings and follow-up items

Conditions noted in the daily reports that the client should be aware of, each tied to the photo or video that records it. None of these affect the completion of the duct cleaning itself.

Before05/10 14:45 · Omar · 51sFCU unit above ceiling – heavy fouling
Before05/10 14:46 · OmarFCU unit above ceiling – heavy fouling
5 Oct 2026 · Wad Obstetrik & Ginekologi 8A ISO 28 · Level 8

Condensation and biofilm on the main FCU duct

Significant condensation and black staining on the main FCU duct above the ceiling. The section has no access opening or cover, so its interior could not be cleaned.

Follow-up For the client: check the FCU insulation and condensate drainage on this unit. An access opening would be needed to clean this section internally.

In progress05/10 14:41 · Omarexhaust access panel
5 Oct 2026 · Wad Obstetrik & Ginekologi 8A ISO 28 · Level 8

Ceiling in poor condition

Stained and damaged ceiling around the exhaust access panel.

Follow-up Outside this scope; reported for the client's maintenance team.

In progress12/10 16:45 · Omar · 18s
In progress12/10 16:31 · Omar
12 Oct 2026 · Wad Perubatan 10B ISO 27 · Level 10

FCU-side opening obstructed by formwork

Access to the FCU-side ceiling opening was blocked by formwork. The team crossed over from the adjacent staff room / pantry along a beam; nothing was cut or removed. The robot went in from the other side.

Follow-up Completed by the normal procedure. The room was first reported as 9B and corrected to 10B.

No photo
12 Oct 2026 · Wad Obstetrik & Ginekologi 8B ISO 27 · Level 8

Odour noticed

An odour was noticed in the room during the exhaust-side and FCU work. No other difference from the other rooms.

Follow-up For the client's attention.

In progress19/10 14:39 · Omar · 39s
19 Oct 2026 · Wad Ortopedik 11 ISO 27 · Level 11

Water dripping onto the floor

Water was dripping onto the floor. Possible sources: a square tank on the roof, or the FCU side once the ceiling cover was opened (wet insulation visible in the video).

Follow-up Source not confirmed. For the client: check the roof tank and the FCU condensate side.

After19/10 14:33 · OmarFinal BMDT spray at the refitted exhaust louvre (frame at 1s of site video)
19 Oct 2026 · Wad Ortopedik 11 ISO 27 · Level 11

Completion not stated in the daily report

The 19 Oct daily report listed this room as "next" without a completion update.

Follow-up Confirmed complete from the photo record: plenum and diffuser cleaned 14:33 – 14:39 and the BMDT spray applied at the refitted louvre.

In progress19/10 16:09 · Omar · 19s
19 Oct 2026 · Wad Perubatan 10B ISO 28 · Level 10

Exhaust filter housing outside the room

Unlike the other rooms, the exhaust filter housing is located outside the room; the team climbed the wall to reach it.

Follow-up Completed; clear robot video recorded (14 min in the room section).

In progress19/10 18:50 · Omar · 43s
In progress19/10 18:53 · Omar · 16s
19 Oct 2026 · Wad Perubatan 10A ISO 28 · Level 10

Damaged filter opening; filters removed and bagged

The exhaust-side filter opening was slightly damaged but could be opened. Both HEPA filters were removed, photographed and bagged.

Follow-up Record for the client: the opening was already damaged. Filter removal is outside the scope and was done only for the first and last rooms on the timetable. Photos of the bagged filters are on the site team's phone and have been requested.

In progress19/10 15:10 · Omar
19 Oct 2026 · Wad Obstetrik & Ginekologi 8B ISO 28 · Level 8

FCU in good condition

FCU in good condition, no leaking, exhaust plenum generally clean before work.

Follow-up No action.

Evidence notes

Coverage, inferences and open items

Photos requested from the site crew

RoomStageRequested
NICU (Neonatal Intensive Care Unit) ISO 2AfterCompletion photo of the refitted diffuser / room
ICU (Intensive Care Unit) ISO 7SanitisationFogging photo or video
ICU (Intensive Care Unit) ISO 7BeforeDiffuser / louvre before cleaning
ICU (Intensive Care Unit) ISO 7In progressCleaning in progress
ICU (Intensive Care Unit) ISO 7AfterCompletion photo
Wad Pediatrik 12 ISO 17SanitisationFogging photo or video
NICU (Neonatal Intensive Care Unit) ISO 1BeforeDiffuser / louvre before cleaning
Wad Ortopedik 11 ISO 28SanitisationFogging photo or video
Wad Perubatan 10B ISO 27SanitisationFogging photo or video
Wad Perubatan 10A ISO 28FiltersPhotos of the two removed HEPA filters (bagged), 19 Oct evening

Source material: site camera roll (21 Sep – 19 Oct 2026), the crew's WhatsApp media, the AWC shutdown schedule, the ISO room layout drawings and the weekly room lists. Every file used here is kept in the organised folder, grouped by day and room and prefixed with its stage.